PARKING STRUCTURES
14 53rd Street
Brooklyn, NY 11232

SCOPE OF WORK
- ▸Concrete Encasement Repair
- ▸Slab-on-Grade Repair
- ▸Garage Ramp Partial Replacement
- ▸Trench Drain Replacement
PROJECT METRICS
| $85,343 Contract Sum — 100% Complete |
| Garage Ramp Partial Replacement & Trench Drain |
Project Overview
14 53rd Street is a parking garage restoration project by Royce CM in Brooklyn, NY, completed and closed out with zero balance remaining.
Scope of Work
- Cracked/deteriorated/spalled concrete encasement and ceiling repair
- Cracked and spalled slab-on-grade repair
- Rusted steel beam/header repair
- Deteriorated brick masonry repair
- Cleanout & test of existing drains / sump pits
- Driveway entrance concrete work
- Garage Ramp Partial Replacement and Trench Drain and Concrete Replacement
Project Metrics
- $85,343 Contract Sum — 100% Complete, fully paid out
Project scope and metrics above are self-reported by Royce CM based on internal project records.